AN ACT
To require approval for the construction, connection, operation, or
maintenance of oil or natural gas pipelines or electric transmission
facilities at the national boundary of the United States for the import
or export of oil, natural gas, or electricity to or from Canada or
Mexico, and for other purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``North American Energy Infrastructure
Act''.
SEC. 2. FINDING.
Congress finds that the United States should establish a more
uniform, transparent, and modern process for the construction,
connection, operation, and maintenance of oil and natural gas pipelines
and electric transmission facilities for the import and export of oil
and natural gas and the transmission of electricity to and from Canada
and Mexico, in pursuit of a more secure and efficient North American
energy market.
SEC. 3. AUTHORIZATION OF CERTAIN ENERGY INFRASTRUCTURE PROJECTS AT THE
NATIONAL BOUNDARY OF THE UNITED STATES.
(a) Authorization.--Except as provided in subsection (c) and
section 7, no person may construct, connect, operate, or maintain a
cross-border segment of an oil pipeline or electric transmission
facility for the import or export of oil or the transmission of
electricity to or from Canada or Mexico without obtaining a certificate
of crossing for the construction, connection, operation, or maintenance
of the cross-border segment under this section.
(b) Certificate of Crossing.--
(1) Requirement.--Not later than 120 days after final
action is taken under the National Environmental Policy Act of
1969 (42 U.S.C. 4321 et seq.) with respect to a cross-border
segment for which a request is received under this section, the
relevant official identified under paragraph (2), in
consultation with appropriate Federal agencies, shall issue a
certificate of crossing for the cross-border segment unless the
relevant official finds that the construction, connection,
operation, or maintenance of the cross-border segment is not in
the public interest of the United States.
(2) Relevant official.--The relevant official referred to
in paragraph (1) is--
(A) the Secretary of State with respect to oil
pipelines; and
(B) the Secretary of Energy with respect to
electric transmission facilities.
(3) Additional requirement for electric transmission
facilities.--In the case of a request for a certificate of
crossing for the construction, connection, operation, or
maintenance of a cross-border segment of an electric
transmission facility, the Secretary of Energy shall require,
as a condition of issuing the certificate of crossing for the
request under paragraph (1), that the cross-border segment of
the electric transmission facility be constructed, connected,
operated, or maintained consistent with all applicable policies
and standards of--
(A) the Electric Reliability Organization and the
applicable regional entity; and
(B) any Regional Transmission Organization or
Independent System Operator with operational or
functional control over the cross-border segment of the
electric transmission facility.
(c) Exclusions.--This section shall not apply to any construction,
connection, operation, or maintenance of a cross-border segment of an
oil pipeline or electric transmission facility for the import or export
of oil or the transmission of electricity to or from Canada or Mexico--
(1) if the cross-border segment is operating for such
import, export, or transmission as of the date of enactment of
this Act;
(2) if a permit described in section 6 for such
construction, connection, operation, or maintenance has been
issued;
(3) if a certificate of crossing for such construction,
connection, operation, or maintenance has previously been
issued under this section; or
(4) if an application for a permit described in section 6
for such construction, connection, operation, or maintenance is
pending on the date of enactment of this Act, until the earlier
of--
(A) the date on which such application is denied;
or
(B) July 1, 2016.
(d) Effect of Other Laws.--
(1) Application to projects.--Nothing in this section or
section 7 shall affect the application of any other Federal
statute to a project for which a certificate of crossing for
the construction, connection, operation, or maintenance of a
cross-border segment is sought under this section.
(2) Natural gas act.--Nothing in this section or section 7
shall affect the requirement to obtain approval or
authorization under sections 3 and 7 of the Natural Gas Act for
the siting, construction, or operation of any facility to
import or export natural gas.
(3) Energy policy and conservation act.--Nothing in this
section or section 7 shall affect the authority of the
President under section 103(a) of the Energy Policy and
Conservation Act.
SEC. 4. IMPORTATION OR EXPORTATION OF NATURAL GAS TO CANADA AND MEXICO.
Section 3(c) of the Natural Gas Act (15 U.S.C. 717b(c)) is amended
by adding at the end the following: ``No order is required under
subsection (a) to authorize the export or import of any natural gas to
or from Canada or Mexico.''.
SEC. 5. TRANSMISSION OF ELECTRIC ENERGY TO CANADA AND MEXICO.
(a) Repeal of Requirement To Secure Order.--Section 202(e) of the
Federal Power Act (16 U.S.C. 824a(e)) is repealed.
(b) Conforming Amendments.--
(1) State regulations.--Section 202(f) of the Federal Power
Act (16 U.S.C. 824a(f)) is amended by striking ``insofar as
such State regulation does not conflict with the exercise of
the Commission's powers under or relating to subsection
202(e)''.
(2) Seasonal diversity electricity exchange.--Section
602(b) of the Public Utility Regulatory Policies Act of 1978
(16 U.S.C. 824a-4(b)) is amended by striking ``the Commission
has conducted hearings and made the findings required under
section 202(e) of the Federal Power Act'' and all that follows
through the period at the end and inserting ``the Secretary has
conducted hearings and finds that the proposed transmission
facilities would not impair the sufficiency of electric supply
within the United States or would not impede or tend to impede
the coordination in the public interest of facilities subject
to the jurisdiction of the Secretary.''.
SEC. 6. NO PRESIDENTIAL PERMIT REQUIRED.
No Presidential permit (or similar permit) required under Executive
Order No. 13337 (3 U.S.C. 301 note), Executive Order No. 11423 (3
U.S.C. 301 note), section 301 of title 3, United States Code, Executive
Order No. 12038, Executive Order No. 10485, or any other Executive
order shall be necessary for the construction, connection, operation,
or maintenance of an oil or natural gas pipeline or electric
transmission facility, or any cross-border segment thereof.
SEC. 7. MODIFICATIONS TO EXISTING PROJECTS.
No certificate of crossing under section 3, or permit described in
section 6, shall be required for a modification to the construction,
connection, operation, or maintenance of an oil or natural gas pipeline
or electric transmission facility--
(1) that is operating for the import or export of oil or
natural gas or the transmission of electricity to or from
Canada or Mexico as of the date of enactment of the Act;
(2) for which a permit described in section 6 for such
construction, connection, operation, or maintenance has been
issued; or
(3) for which a certificate of crossing for the cross-
border segment of the pipeline or facility has previously been
issued under section 3.
SEC. 8. EFFECTIVE DATE; RULEMAKING DEADLINES.
(a) Effective Date.--Sections 3 through 7, and the amendments made
by such sections, shall take effect on July 1, 2015.
(b) Rulemaking Deadlines.--Each relevant official described in
section 3(b)(2) shall--
(1) not later than 180 days after the date of enactment of
this Act, publish in the Federal Register notice of a proposed
rulemaking to carry out the applicable requirements of section
3; and
(2) not later than 1 year after the date of enactment of
this Act, publish in the Federal Register a final rule to carry
out the applicable requirements of section 3.
SEC. 9. DEFINITIONS.
In this Act--
(1) the term ``cross-border segment'' means the portion of
an oil or natural gas pipeline or electric transmission
facility that is located at the national boundary of the United
States with either Canada or Mexico;
(2) the term ``modification'' includes a reversal of flow
direction, change in ownership, volume expansion, downstream or
upstream interconnection, or adjustment to maintain flow (such
as a reduction or increase in the number of pump or compressor
stations);
(3) the term ``natural gas'' has the meaning given that
term in section 2 of the Natural Gas Act (15 U.S.C. 717a);
(4) the term ``oil'' means petroleum or a petroleum
product;
(5) the terms ``Electric Reliability Organization'' and
``regional entity'' have the meanings given those terms in
section 215 of the Federal Power Act (16 U.S.C. 824o); and
(6) the terms ``Independent System Operator'' and
``Regional Transmission Organization'' have the meanings given
those terms in section 3 of the Federal Power Act (16 U.S.C.
796).
Passed the House of Representatives June 24, 2014.
Attest:
KAREN L. HAAS,
Clerk.
Calendar No. 442
113th CONGRESS
2d Session
H. R. 3301
_______________________________________________________________________
AN ACT
To require approval for the construction, connection, operation, or
maintenance of oil or natural gas pipelines or electric transmission
facilities at the national boundary of the United States for the import
or export of oil, natural gas, or electricity to or from Canada or
Mexico, and for other purposes.
_______________________________________________________________________
June 26, 2014
Read the second time and placed on the calendar