[Congressional Bills 117th Congress]
[From the U.S. Government Publishing Office]
[H. Res. 1326 Reported in House (RH)]
<DOC>
House Calendar No. 141
117th CONGRESS
2d Session
H. RES. 1326
[Report No. 117-535]
Of inquiry requesting the President, and directing the Secretary of
Energy, to transmit to the House of Representatives certain information
relating to plans to protect baseload bulk power system generation and
transmission to maintain bulk power system reliability.
_______________________________________________________________________
IN THE HOUSE OF REPRESENTATIVES
August 26, 2022
Mr. Pence submitted the following resolution; which was referred to the
Committee on Energy and Commerce
September 30, 2022
Reported adversely from the Committee on Energy and Commerce, referred
to the House Calendar, and ordered to be printed
_______________________________________________________________________
RESOLUTION
Of inquiry requesting the President, and directing the Secretary of
Energy, to transmit to the House of Representatives certain information
relating to plans to protect baseload bulk power system generation and
transmission to maintain bulk power system reliability.
Resolved, That the President is requested, and the Secretary of
Energy is directed, to transmit to the House of Representatives, not
later than 14 days after the date of adoption of this resolution,
copies of all documents, memoranda, and advisory legal opinions,
including notes from meetings, memos, and telephone and electronic mail
records, to the extent that any such one or more items are within the
possession of the President or the Secretary, respectively, and refer
or relate to the following:
(1) How the Secretary of Energy plans to respond to the
insufficient baseload electricity generation and transmission
described by the North American Electric Reliability
Corporation in the document titled ``2022 Summer Reliability
Assessment'' (May, 2022) to ensure the bulk power system is
able to provide reliable, affordable, and dispatchable baseload
electricity generation and transmission.
(2) Correspondence between the Secretary of Energy and bulk
power system operators, the Chair of the Federal Energy
Regulatory Commission, and the Administrator of the
Environmental Protection Agency relating to how the generation
and transmission of electricity in the bulk power system, and
the reliability of the bulk power system, is expected to be
affected by--
(A) premature retirements or temporary closures of
baseload electric generating units as a result of
enforcement actions with respect to the requirements of
section 257.103(f) of title 40, Code of Federal
Regulations;
(B) any approved demonstrations for extensions
submitted under section 257.103(f) of title 40, Code of
Federal Regulations (relating to alternative closure
requirements for coal combustion residuals landfills
and surface impoundments); and
(C) finalization of the proposed rule published by
the Administrator of the Environmental Protection
Agency on April 6, 2022, titled ``Federal
Implementation Plan Addressing Regional Ozone Transport
for the 2015 Ozone National Ambient Air Quality
Standard'' (87 Fed. Reg. 20036).
House Calendar No. 141
117th CONGRESS
2d Session
H. RES. 1326
[Report No. 117-535]
_______________________________________________________________________
RESOLUTION
Of inquiry requesting the President, and directing the Secretary of
Energy, to transmit to the House of Representatives certain information
relating to plans to protect baseload bulk power system generation and
transmission to maintain bulk power system reliability.
_______________________________________________________________________
September 30, 2022
Reported adversely from the Committee on Energy and Commerce, referred
to the House Calendar, and ordered to be printed