An Act
To require the Director of the Office of Management and Budget to
approve or deny spend plans within a certain amount of time, and for
other purposes.
Be it enacted by the Senate and House of Representatives of the
United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the ``Fishery Improvement to Streamline
untimely regulatory Hurdles post Emergency Situation Act'' or the
``FISHES Act''.
SEC. 2. SPEND PLANS.
Section 312(a)(6) of the Magnuson-Stevens Fishery Conservation and
Management Act (16 U.S.C. 1861a(a)(6)) is amended--
(1) in subparagraph (D), to read as follows:
``(D) Spend plans.--
``(i) In general.--To receive an allocation from funds
available under paragraph (9), a requester with an
affirmative fishery resource disaster determination shall
submit a spend plan to the Secretary, not more than 120
days after receiving notification that funds are available,
that shall include the following information, if
applicable:
``(I) Objectives and outcomes, with an emphasis on
addressing the factors contributing to the fishery
resource disaster and minimizing future uninsured
losses, if applicable.
``(II) Statement of work.
``(III) Budget details.
``(ii) Review.--
``(I) In general.--The Secretary shall review a
spend plan submitted under clause (i) to determine if
it is complete and provide notice within 10 days.
``(II) Incomplete spend plan.--If the Secretary
determines that a spend plan submitted under clause (i)
is not complete, when providing the notice required by
subclause (I), the Secretary shall provide a detailed
description of the information that is necessary for
the spend plan to be determined complete.''; and
(2) in subparagraph (F)(i), to read as follows:
``(i) Availability.--
``(I) Timeline.--Funds shall be made available to
grantees not later than 90 days after the date the
Secretary receives a complete spend plan.
``(II) Review of completed spend plan and
apportionment of funds.--If so requested, the Director
of the Office of Management and Budget may review a
completed spend plan concurrently with the Secretary.
The Director of the Office of Management and Budget may
not delay the timeline described in subclause (I).''.