To direct the Secretary of the Army to seek to enter into certain contracts regarding the self-protective adaptive roller kit II system.


IN THE HOUSE OF REPRESENTATIVES
September 20, 2010

Mr. Taylor (for himself and Mr. Skelton) introduced the following bill; which was referred to the Committee on Armed Services


A BILL

To direct the Secretary of the Army to seek to enter into certain contracts regarding the self-protective adaptive roller kit II system.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,

SECTION 1. Self-protective adaptive roller kit II system.

(a) Purchase or lease of technical data package.—Not later than 10 days after the date of the enactment of this Act, and in accordance with subsection (b)(2), the Secretary of the Army shall seek to enter into a contract with Pearson Engineering Limited of Newcastle, the United Kingdom, for the purchase or unlimited lease of the self-protective adaptive roller kit II system technical data package.

(b) Procurement of system.—

(1) PRODUCTION.—Not later than three days after the date on which the Secretary enters into a contract under subsection (a), the Secretary shall seek to enter into contracts with any domestic manufacturer with capacity to produce the self-protective adaptive roller kit II system for the production of such system.

(2) TERMINATION OF TECHNICAL DATA PACKAGE CONTRACT.—If no contract is entered into under paragraph (1) by the date that is 30 days after the date on which the Secretary enters into a contract under subsection (a), the Secretary shall terminate the contract entered into under subsection (a).

(c) Panama City generation three.—

(1) FAILURE TO ENTER INTO TECHNICAL DATA PACKAGE CONTRACT.—If no contract is entered into under subsection (a) by the date that is 30 days after the date of the enactment of this Act, the Secretary of the Army shall coordinate with the Secretary of the Navy to procure the Panama City Generation Three roller system.

(2) FAILURE TO ENTER INTO PRODUCTION CONTRACT.—If no contract is entered into under subsection (b)(1) by the date that is 30 days after the date on which the Secretary enters into a contract under subsection (a), the Secretary of the Army shall coordinate with the Secretary of the Navy to procure the Panama City Generation Three roller system.

(d) Self-protective adaptive roller kit II system technical data package defined.—In this section, the term “self-protective adaptive roller kit II system technical data package” means the technical drawings, specifications, and other engineering data necessary for the production of the self-protective adaptive roller kit II system.